Summary: Equinix will be replacing cabling on the DX cooling systems at PE2 to improve reliability and performance.
Impact: Power: - No impact expected. - All loads will remain on utility power and protected by primary UPS systems. - Full power system redundancy will be maintained throughout.
Cooling: - Cooling system redundancy will be temporarily reduced. - Only one DX unit will be taken offline at a time to allow for safe operating temperatures during the maintenance window.
Mitigation Measures: - Work will be performed sequentially to avoid any significant impact to the operating environment. - On-site personnel will actively monitor systems throughout the maintenance period.
Customer Action: No action is required from customers at this time. All work will be closely coordinated and monitored by Equinix and their approved vendors.
If you have any concerns or require further information, please contact our support team.
Posted Jul 07, 2025 - 10:36 AEST
This scheduled maintenance affects: Regions (Perth) and Data Centres (Equinix PE2).